The Central Lyon Community School District will be completing a variety of concrete projects at the Borman Forster Ball Complex. Detailed plans and specifications are available for download below or may be picked up in the high school office at 1010 S. Greene Street, Rock Rapids, Iowa. Interested parties should direct questions to Brent Jorth, Superintendent.
The timeline for the project will proceed as follows:
- Thursday, July 22, 2021
- Drawings released to bidders
- Thursday, August 5, 2021
- 1:00 p.m. – Bids Due
- Thursday, August 12, 2021
- 7:00 p.m. – Central Lyon School Board considers approval of bids
- Saturday, September 18, 2021
- Construction Complete